Project update2026-10-21 · 5 min read

Purbachal Tower 02 tops out at level 38

Crew in helmets at the topping-out briefing
Topping-out briefing, level 38, 21 October 2026

At 06:40 on 21 October the last bucket went into the core at level 38, one hundred and fifty-two days after the slip-form started climbing. The baseline programme said 1 November. We were eleven days early, and nobody got hurt getting there.

The cycle

The tower runs on two clocks. The core climbs on a four-day slip-form cycle: strike, climb, fix, pour. The floor plates follow on a six-day cycle using our own aluminium system formwork, two floors behind the core. If either clock slips, the other one waits, so the whole job is really a question of never letting either slip.

For 152 days neither did. The reasons are boring, which is the point:

  • Rebar cages for the core walls were pre-fabricated in the Narayanganj yard and delivered as the slip-form reached each level, so nothing was tied in the air.
  • Two concrete pumps on site at all times, one on standby, both tested each morning before the first pour.
  • A batching plant 1.8 km away that we own, so the mix never queued behind someone else's order.
  • Night pours in April and May to keep slab temperatures under control.
Core and cranes at level 30
Core at level 30, August. The two luffing cranes were climbed eleven times each.

What nearly went wrong

Week 14. A pump line blocked at level 19 with 40 m³ already in the truck. The standby pump was set up in 35 minutes and the pour finished at 23:10 instead of 21:00. That is the only reason this post says eleven days and not twelve.

A programme is not a promise about the future. It is a list of the things you have already decided not to leave to chance.

Next

Façade installation is on level 12 and climbing; fit-out starts on the podium in December. Handover is still May 2026. We will publish the next update when the curtain wall closes at level 38.